21 Mar 05: They survey the scene—as the road surfacing continues below us
|
|
|
|
21 Mar 05: The little digger arrives...
|
|
|
|
21 Mar 05: Excavation begins
|
|
|
|
26 Mar 05: The little digger gives up and the big one arrives...
|
|
|
|
...and just makes it through to the terrace
|
|
|
|
26 Mar 05: A big hole
|
|
|
|
6 Apr 05: The foundations are being laid
|
|
|
|
|
8 Apr 05: The walls are rising
|
|
|
|
11 Apr 05: The vigas arrive for the base
|
|
|
|
12 Apr 05: The blocks are added to complete the base
|
|
|
|
13 Apr 05: And still the walls are rising...
|
|
|
|
14 Apr 05: They have been working round the far side too!
|
|
|
|
15 Apr 05: The walls have obviously risen as far as they need
|
|
|
|
15 Apr 05: And this is what is going on round the other side
|
|
|
|
|
18 Apr 05: See the pipes for the pump and the walls for the pumphouse!
|
|
|
|
19 Apr 05: There is a lot of reinforcing mesh in there now
|
|
|
|
20 Apr 05: More reinforcing, more plumbing, and a roof for the pumphouse
|
|
|
|
20 Apr 05: Lights in the trough and rendering of the walls
|
|
|
|
25 April 05: This is how they started the spraying...
|
|
|
|
...and this is during the process...
|
|
|
|
...and this is it finished!
|
|
|
|
|
27 Apr 05: The little digger returns to backfill - and see the new boundary wall behind it!
|
|
|
|
...it doesn't look quite so big with the earth back round it
|
|
|
|
3 May 05: The beginning of the cloisters (nearer) and the new boundary wall behind
|
|
|
|
4 May 05: The next stage of the cloisters...
|
|
|
|
...and a close-up for the engineers out there
|
|
|
|
...and a nice new gate which Ken is in the process of fitting in the nice new wall
|
|
|
|
5 May 05: The beginning of the roof
|
|
|
|
|
6 May 05: Aren't they getting on well? And it feels cool in there already
|
|
|
|
9 May 05: The roof is nearly finished and the rendering is coming on well
|
|
|
|
10 May 05: The roof is finished and the rendering has moved to the front wall
|
|
|
|
11 May 05: A wider view...
|
|
|
|
12 May 05: The beginning of the base for the shade deck
|
|
|
|
13 May 05: Where the cloister, the steps and the ramp all meet
|
|
|
|
16 May 05: Terracotta tiles on the concrete; dark blue tiles in the pool and bronze cranes in the centrepiece...
|
|
|
|
|
17 May 05: The red former is in place for the coronación (edging) of the pool tomorrow
|
|
|
|
...and the bases for all the tiling are in place
|
|
|
|
18 May 05: The coronación is complete and the colour is good, but...
|
|
|
|
...most of the tiles have had to come up again because the base is not square
|
|
|
|
19 May 05: I do like these tiles...
|
|
|
|
20 May 05: They have started on the complementary tiling and it looks good
|
|
|
|
23 May 05: The tiling of the terrace is coming on nicely
|
|
|
|
|
24 May 05: The tiling continues to spread...
|
|
|
|
25 May 05: New finials on wall...we are going to buy something to go on the other side
|
|
|
|
26 May 05: The gravel is good, but they're still waiting for the tiles to finish the cloister
|
|
|
|
27 May 05: Now he has the tiles he is getting on like a house on fire...
|
|
|
|
28 May 05: A little shade to keep the tile cement cool - and the workers as well...
|
|
|
|
...and the cat checks that the quality of the tiling is satisfactory
|
|
|
|
31 May 05: The tiling of the pool is done, waiting the final grouting...
|
|
|
|
|
...and the tile panel has finally arrived - laid by Paco, the master tiler!
|
|
|
|
2 Jun 05: And this is it all finished...ready for cleaning, painting, planting, dressing...
|
|
|
|
See Pool Terrace under AtoZ for the continuing project.
|
|
|
|
3 Jun 05: Having thought it was all done they came back, cleaned and then built this!
|
|
|